The lido under construction -
1934
It was finally decided favourably by a majority vote and the Council
sought a loan from the Ministry for Health.
Due to the council debate, which
was carried over several committee meetings, the scheduled date for
commencement of the project was delayed and the work could not be
started till the late autumn of 1934, which meant the hard work of
digging out the pool had to be carried out during
the worst weather months of the year.
For some time while the work was
in progress this site was almost knee-deep in mud, seriously
delaying the job and during the excavation of the pool itself an
extensive vein of peat was uncovered, necessitating many more tons
of concrete being used than was originally contemplated. This method
of combating the layer of peat would later cause additional problems
for the Charitable Trust.
|